 Support Services Projects:
Minimize
Medulla Fire Station Reconstruction

Status: Underway

Construction of the new station on Ewell Road is nearing completion.  Crews should be in the new station before Thanksgiving.  Until then, they are operating out of Station 20 on Ewell Road.

 
Peace Creek Fire / EMS Station

 Status: Completed

The recently opened Peace Creek Fire/EMS Station allowed for the relocation of the existing apparatus and crew from the old Rifle Range fire station.  The project was completed on time and under budget and is part of the Fire Services 10 Year Business Plan.

 
Loughman Fire Station Remodel

 Status: Completed

The remodel of Fire Station 18 in Loughman has been completed and crews have moved back in.  The remodel was necessary to allow for the staffing of the fire station on a 24 hour basis.  The project was completed on time and within budget.

 
Lake Hamilton Fire Station Remodel

Status: Completed

The remodel of Fire Station 35 consists of the addition of crew quarters to allow for the station to be staffed 24/7.  The interior of the appratus bays are being remodeled to allow for the housing of additional apparatus as well as the repair of the apparatus bay floor.

 

 